  气浮机的安装

  气浮机安装前,必须用混凝土打好地基。也可以架空安装,但基础必须能承担设备运行时的重量(箱体内注满水的重量)。设备位后需要找水平气浮机需设清洗用下水道,也可以直接采用管道接至调节池,以便冲洗气浮池的水排出。废水进口与反应池之间的连接管道,要越短越好,以免絮凝体在管道中被破坏。清水出口可连接清水池,也可直接与下道处理设备相接。悬浮物出口可接至污泥浓缩池或带式压滤机经污泥脱水机处理。电器箱一般应放置在扶梯侧面加防护防雨装置。

  气浮机的调试

  气浮机试前,应做好以下准备工作:1、要清洗水池内所有的杂质、焊渣。2、对水泵及空压机等需要润滑部位进行加油润滑。3、接通电源,启动溶气泵,检查转向是否与箭头所标方向一致。用手动控制启动空压机,检查空压机运转是否正常,发现异常情况应及时查清原因。4、按下桁车式刮渣机开关。运行到对后在行程撞块作用下,刮渣机面反向行走,直到污泥槽,行程撞块将刮板翻起,按下停止按钮,停止刮沫。5、调节加药装置到佳状态使污水与悬浮物分离,以上简单介绍了气浮机的安装与调试下篇文章介绍气浮机的运行。气浮机调试与安装气浮机的一些注意注意事项。

 

我公司专业生产销售气浮机刮吸泥机气浮气浮设备砂滤罐本文由www.wxwoma.com提供

 The installation of air flotation machine

Air flotation machine before installation, must lay a foundation in concrete. Also can be installed overhead, but base must be able to bear the weight of the equipment run time (the weight of the casing filled with water). Equipment in place after the need to find a level of the need for clean air flotation machine with the sewer, also can be directly use pipe connected to adjust pool, in order to flush air flotation pool of water. Import the connection between the pipe and reaction pool, waste water should be as short as possible, lest the flocculation body destruction in the pipeline. Water outlet can connect clear water reserviors, also can be directly into the next processing equipment. Suspended exports can connect to the sludge concentration pool or belt type filter press sludge dewatering machine processing. The electrical box should be generally placed in add protective rain gear on the side of the escalator.

Air flotation machine debugging

Air flotation machine to try before, should make preparations for the following: 1, to clean all the impurities, welding slag pool. 2, the water pump and air compressor lubrication part need for lubrication. 3, connected to the power supply, start the dissolved air pump, and check whether in line with the arrow direction. Use manual control to start the air compressor, check whether the compressor running normally, found the abnormal situation should be timely find out the reason. 4, press the girder vehicle type sludge scraper switch. Run to, under the action of the collision block the trip after scraping the slag machine surface reverse to walk, until the sludge tank, schedule collision block up the scraper at, press the stop button, stop blowing foam. 5, adjust the dosing device to best make sewage and separation of suspended solids, the above simple introduced the air floating machine installation and debugging next article introduces the operation of air flotation machine. Air flotation machine debugging and installation of air floatation machine attention some matters needing attention.